48. What emergency measures should be taken if the Chinese drill pipe breaks during drilling?
Answer: ①When the fish head is below the turntable surface, quickly retrieve the drill string by connecting a drill pipe to the slip-type fishing spear and lowering it to grab the tool.
② If the fish head is above the rotary table surface, first unscrew and lift the square drill pipe out of the wellhead, then lower the drill pipe to engage and retrieve the downhole drilling tools.
49. What are the signs when a drill pipe breaks during drilling? How should it be identified and handled?
Answer: Phenomenon:
① Suspended weight decreases, pump pressure drops;
② The rotary table load becomes lighter, with no penetration rate;
③ After being lifted upward and lowered downward, the rear entry changes.
Method of judgment:
① Lift the drill string to check the weight indicator and suspended weight;
② Check whether the mud pump and pressure gauge are functioning properly;
③ Verify the input.
Treatment method: Immediately pull out the drill string and determine the appropriate fishing tools and measures based on the condition of the dropped fish.
50. What phenomena occur when the drill string breaks during drilling? How should it be identified and handled?
Answer: Phenomenon:
① Pump pressure drops, while suspended weight shows no significant decrease;
② The rotary table load becomes lighter, with no penetration rate;
③ After being lifted upward and lowered downward, the structure remains unchanged.
Method of judgment:
① Check whether the mud pump and pressure gauge are functioning properly and intact, and document the process and details of any pressure drop.
② Turntable load conditions;
③ Check the drill string by touching it with your hand to get a sense of the fish head condition.
Treatment method: First, address the stuck pipe. If there is no effect, immediately pull out of hole and determine the appropriate fishing tools and measures based on the condition of the fallen object.
51. Why does well leakage occur? What are the different types of well leakage? How can it be identified? And how should it be handled?
Answer: The reasons are:
① The upper strata are loose, allowing for fast drilling speeds; however, the drill cuttings in the drilling fluid are abundant and have high density. If the pump is started too aggressively during single-joint connections, it can easily lead to wellbore pressure buildup and potential losses.
② In permeable formations, excessively high drilling fluid density can cause fracturing of the formation.
③ Drilling through fault zones, fractures, or solution cavities.
④ Improper engineering practices, such as lowering the drill string too quickly, can lead to significant pressure surges, resulting in sticking, getting stuck, or issues like pump activation in narrow wellbores, excessive pump speed, overly high pump pressure, and even pump blockages.
Well leakage can be classified into three types based on the rate of loss:
① Permeability loss, with a leakage rate of less than 5 cubic meters per hour;
② Fracture-induced fluid loss, with a loss rate exceeding 5 cubic meters per hour;
③ Cavity-type fluid loss, where fluid enters but does not exit, with a loss rate exceeding 100 cubic meters per hour.
Judging Well Leakage:
① Mud pool liquid level drops;
② Wellbore experiences more inflow than outflow; in severe cases, drilling fluid fails to return.
③ During drilling, if the drilling rate suddenly increases or the drill string becomes unloaded, accompanied by a drop in pump pressure, well leakage or well surging is likely to occur.
Well control during lost circulation: If the loss rate exceeds 5 cubic meters per hour—especially in cases of severe losses—immediately organize a forced drill-out operation, simultaneously circulating drilling fluid at high displacement rates. After pulling out the drill string, develop a well-defined leak-stopping strategy based on the specific conditions of the lost circulation. Before running the drill string back into the well to address the leak, ensure thorough preparation of anti-sticking measures, adequate drilling fluid circulation, and sufficient materials for both the forced drill-out and the subsequent leak-sealing process. Finally, once the drill string is reinserted, apply tailored leak-stopping techniques suited to the particular type of loss encountered.
Leak-stopping methods:
① For permeability-induced losses, appropriate measures include reducing the drilling fluid density, decreasing the flow rate, and adding polymers, CMC, one-way pressure sealants, and other chemicals to increase the fluid viscosity, thereby minimizing fluid loss and preventing issues during trips.
② For fractures and fault-related losses, use leak-stopping materials. Depending on the rate of leakage, you can inject rice husks, sawdust, cottonseed hulls, shell powder, or quick-setting clay (adapting to local conditions and utilizing readily available resources), or alternatively, apply gel-like cement or lime milk to seal the leaks.
③ For solution-type losses, it's generally necessary to first fill the voids with gravel, bricks, tile fragments, and mud balls, followed by plugging the leak with quick-setting cement or adopting a method that allows fluid entry but prevents exit, thereby forcefully penetrating the leakage layer. Afterward, casing is run to seal off the leak.
No matter which method is used to seal the leak, preventing drillstring sticking must be the top priority, as a loss of drilling fluid due to the well leak can cause the upper, softer formations to collapse and become stuck. After passing through the leaking layer and successfully sealing it, pumping should never be initiated at the location of the leak under any circumstances.
Measures for addressing known leak zones: Drill to about 50 meters above the known leak layer, then stop drilling. Pull out the drill string and switch to a simplified drilling tool assembly, minimizing the use of drill collars and avoiding the installation of centralizers. Select appropriate standard roller cones, and do not install water jets. Ensure all equipment is thoroughly inspected and maintained, and conduct comprehensive design reviews and technical briefings. Prepare ample leak-sealing materials and drilling fluid additives, stockpiling enough drilling fluid—enough to fill twice the volume of the wellbore. Ideally, perform the leak-sealing operation during daylight hours.
52. What is keyseat sticking? What are its characteristics? How can it be prevented and handled?
Answer: During drilling operations, significant horizontal forces are generated in well sections with large changes in the wellbore's total angle, causing the drill string to rotate tightly against this area. As the drill string is raised and lowered, it scrapes back and forth here, gradually wearing a narrow groove—known as a "keyseat"—into the wellbore wall. The diameter of this groove is slightly larger than the drill pipe joint but smaller than both the drill collar and the drill bit. When attempting to pull the drill string out of the hole, the drill collar or drill bit becomes stuck at the bottom of the keyseat, a condition commonly referred to as "keyseating."
Features:
① Card Before drilling, the drill string moves freely and smoothly downward; however, when pulling out of the hole, the sticking point tends to be fairly consistent, and the drill bits often show signs of uneven wear. When attempting to lift the drill string during a stuck situation, it can still be lowered or rotated—but it simply cannot be retrieved upward.
② Circulation is possible and pump pressure is normal; even after getting stuck, starting the pump isn’t difficult, and the circulating pump pressure remains steady.
Preventive measures:
① Ensure wellbore quality and avoid sections with sharp bends;
② Use high-efficiency drill bits to increase drilling speed, reduce the number of trips in and out of the hole, and complete drilling before keyseat formation occurs.
③ In well sections with significant full-hole angular changes, frequent reaming should be performed to promptly eliminate keyseat formations.
④ When pulling out of the hole into the keyseat section, raise the drill string at a slow speed, closely monitoring the weight indicator; high-speed lifting that could cause sticking is strictly prohibited.
⑤ Choose drill string configurations wisely, using grooving tools and impact devices whenever possible.
Mitigation measures:
① If the drill string can be freed without breaking the bit, lower it to dislodge the stuck tool; then, rotate it in different orientations while applying a slight upward or downward pull, and abruptly engage the rotary table to cause the drill string to swing and pop out of the keyway.
② In cases of severe stuck pipe, first circulate and properly treat the drilling fluid, then carefully work upward from the keyseat to retrieve the drill string. Next, lower the drill pipe equipped with a keyseat breaker and a down-the-hole hammer, make proper connections, apply the down-the-hole hammer to free the stuck pipe, and finally use the keyseat breaker to dismantle the keyseat before pulling out the drill string.
53. What is sticking (pressure differential) stuck pipe? What causes it? How can it be prevented and handled?
Answer: When drilling tools remain inactive underground for an extended period, differential pressure causes them to stick tightly against the wellbore wall, resulting in a type of stuck pipe known as "stick-slip sticking."
The reason is:
① The drill string remains stationary in the well for too long;
② High pressure differential within the well;
③ The drilling fluid performs poorly, exhibiting high fluid loss, thick mud cake, and a high coefficient of friction.
④ Poor drilling fluid purification, especially when leak-sealing mud containing fibrous materials is used, can more easily lead to sticking and seizing.
⑤ Drilling fluid performance suddenly deteriorates after water-based or gypsum-based treatment;
⑥ Poor wellbore quality or directional wells.
Preventive measures:
① Use drilling fluids with excellent anti-galling performance, minimizing viscosity and fluid loss as much as possible, reducing the coefficient of friction, and enhancing the compressibility of the mud cake.
② Employ near-balanced pressure drilling to manage the pressure differential.
③ Add crude oil, non-fluorescent lubricants, graphite powder, or friction-reducing plastics, glass microbeads, and surfactants to the drilling fluid to lower the mud cake's viscosity coefficient.
④ Never let go of the control handle—promptly move the drill string;
⑤ Ensure proper wellbore quality control.
⑥ When encountering special circumstances that prevent normal drilling operations, apply downward pressure on the suspended weight (during drilling) or use an air hoist to pull the rotary table chain—methods designed to prevent sticking and getting stuck.
Handling method:
① In the early stages of sticking, while ensuring safety, vigorously move the drill string (primarily using downward hammering) to try to free the stuck pipe.
②If ineffective, perform a high-displacement well cleaning, properly manage the drilling fluid properties, ensure thorough solids removal, accurately identify the sticking point, precisely calculate the required amount of lubricating agent, and prepare to inject the lubricant, followed by injecting crude oil (or diesel) and acid treatment (suitable for limestone formations) to dissolve and free the stuck pipe.
③ If it remains ineffective, proceed with reaming and reverse-threading or use explosives to loosen the connection before filling the wellbore and drilling laterally.
54. What is pump-induced stuck pipe due to憋漏? What are its causes and symptoms? How can it be prevented and handled?
Answer: When wellbore blockage occurs due to reasons such as井塌 (well collapse) or沉砂 (sand settling), leading to pump pressure buildup that fractures the formation and causes significant drilling fluid loss, resulting in井壁垮塌 (wellbore instability) and ultimately getting the drill string stuck, this type of stuck pipe is referred to as "pump-pressure-induced stuck pipe."
Reason:
① The drilling fluid performance is poor, the wellbore is unstable, and there are signs of collapse in the upper formations during the running-in process.
② For some reason, the upper formation caused irregular wellbore conditions, leading to a sand bridge that blocked the annular space during drill string descent.
③ Rapid drilling causes ground equipment failure, on-site repair of drill string components, and sand settling that blocks the annular space.
④ Start the pump without returning drilling fluid; if the pressure is not high, avoid continuous pumping—this can lead to significant fluid loss, causing severe formation collapse.
Phenomenon: When the pump is turned on, fluid enters but does not exit; the lost-circulation pressure remains low. Upon stopping the pump, backpressure is observed, which slightly decreases after drilling tool movement. However, after repeated pumping cycles, drilling fluid begins to leak extensively into the formation. Initially, the drill string moves freely up and down and rotates smoothly. As the loss increases, resistance develops during upward and downward movements, causing the string to bind or even reverse rotation. In severe cases, the drill string becomes completely stuck in place. Some wells, though initially still movable, eventually get stuck when the string reaches the collapsed section near the wellbore's uppermost zone.
Preventive measures:
① Before pulling out of the hole, adjust the drilling fluid properties to meet the requirements for withdrawal, thoroughly circulate to remove cuttings from the wellbore, and ensure the drill string is properly filled with drilling fluid as specified during the pullout process.
② During the mid-drilling process in long open-hole wells, it's necessary to circulate drilling fluid in sections. Normally, after reaching the bottom of the hole, leave one single drill pipe connected to the square drill stem for reaming all the way to the bottom. Keep the pump displacement low—consider either removing the water valve on the pump or reducing the diesel engine speed—and start the pump in multiple stages. Each time the pump is started, the pump pressure should not exceed 5 MPa. Once drilling fluid begins to return to the surface, gradually increase the pump operation to normal. After starting the pump, closely monitor the pump pressure gauge; if you notice any increase in pump pressure, immediately reduce the displacement to prevent potential issues.
③ If the pump is difficult to start, increase the range of drill string movement and release some return water. If the pump still fails to start after these steps, carefully pull the drill string out of the wellbore until you reach a section with unobstructed circulation, then attempt to restart the pump. Once circulation returns to normal, you can either lower the drill string again or perform reaming operations. (Observe that as the drill string moves upward, the annular fluid level drops, confirming that the annulus remains clear.)
④If the pump pressure becomes excessively high, causing a formation leak, decisively proceed by retrieving the drill string slowly in first gear while continuously circulating drilling fluid. When reaching the wellbore section where collapse has occurred, lift slightly less and lower more frequently, repeatedly moving the string to dislodge collapsed cuttings. Only then should you patiently and gradually pull the string out, carefully avoiding getting it stuck.
Handling: If pump jamming, wellbore leakage, or sticking has already occurred, the only options are either reverse circulation milling followed by back-off, or explosive release of the stuck pipe, followed by wellbore abandonment and sidetracking.
55. What is sand settling and sticking in the drill string? What are its causes, characteristics, preventive measures, and remedial actions?
Answer: When drilling tools are stationary, and after reducing the flow rate or stopping the pump, a large amount of cuttings in the drilling fluid settles and lodges beneath the lower part of the drill string, causing the bit to become stuck—this is known as sand settling-induced bit sticking.
The reason is:
① When drilling through upper strata—especially during clear-water drilling or when the drilling fluid struggles to suspend and carry cuttings effectively—the drilling rate tends to be high, leading to a significant accumulation of cuttings inside the wellbore. As a result, when the pump is stopped, these cuttings rapidly settle and often end up burying the drill bit or even partially obstructing the downhole tools.
②The lower formation suffers from severe cuttings loss and wellbore collapse due to poor cementation, leading to water absorption and swelling, faulting, fractured zones, or significant adjustments in drilling fluid properties—often resulting in poor performance. These conditions can cause the wellbore to enlarge or even form sand bridges. Additionally, during pump shutdown and wellbore quiescence, sand settling easily leads to drillstring sticking.
The phenomenon is: when the drill string is disconnected, severe reverse flow occurs inside the drill pipe; when connecting the square drill pipe and starting the pump, the pump pressure becomes extremely high—sometimes even causing the pump to stall entirely; during upward pulling, the drillstring gets stuck, while downward lowering encounters resistance—and when attempting to rotate the string, it experiences significant torque resistance or simply stalls altogether.
Preventive measures:
① Ensure the installation quality of the circulation and purification systems, and appropriately increase the pump capacity.
② When receiving the drill pipe, organize personnel efficiently to minimize pump downtime as much as possible;
③ If sand settling is observed, reduce the drilling rate, adjust the drilling fluid properties, or stop drilling and perform a high-volume circulation. Resume drilling only after conditions return to normal.
④ In areas with severe erosion and significant cuttings removal in the lower formations, especially when the wellbore diameter is large, it is essential to formulate a high-viscosity drilling fluid with excellent carrying capacity to effectively remove cuttings or stabilize the new wellbore wall. Additionally, pumping and reaming operations should be strictly prohibited in this specific well section.
⑤ When encountering stuck pipe during tripping operations, do not forcibly pull or hammer it—instead, promptly organize circulation and drill string movement. If circulation fails and drilling fluid does not return to the wellhead, immediately stop the pump and release the return flow to loosen the accumulated cuttings. Then, continue moving the drill string, retrieve it from the hole, and finally ream the wellbore to ensure smooth passage.
⑥ When sand settling is detected, appropriately increase the viscosity and gel strength of the drilling fluid to enhance its ability to suspend and carry cuttings. At the same time, pay careful attention to the method of starting the pump to prevent formation breakage or loss circulation.
Treatment methods: Once the drill bit becomes stuck due to sand accumulation, the only options are either reverse circulation with milling followed by back-off, or using explosives to loosen the connection. If milling or shock techniques prove ineffective for freeing the lower portion of the stuck drill string, wellbore sidetracking should be employed instead. The most appropriate approach should always aim to minimize economic losses.
56. What is drill sticking? How should it be handled?
Answer: During drilling, if the brake fails to function properly or an operational mistake causes the drill string to suddenly slip downward, resulting in an instant and excessive drilling pressure, this phenomenon is referred to as "slip drilling."
Treatment methods: Depending on the severity of drill sticking, different measures can be taken. First, check whether the circulating pump pressure is normal. If it is normal, assess the condition of the roller cones—specifically, observe whether there’s a periodic bit-gagging phenomenon during light-pressure, slow-rotation drilling. Next, verify if the make-up and break-out depths are consistent across all connections. If bit-gagging occurs and the make-up depths differ significantly (off by the height of one roller cone), this likely indicates either cone wobbling or a dropped cone; in such cases, immediately pull out of the hole. On the other hand, if light-pressure, slow-rotation drilling proceeds smoothly but becomes normal under heavier pressure, consider reducing the overall time the drill bit is in use to prevent further cone drop.
57. What precautions should be taken when using a soaking agent (oil) after getting stuck?
Answer: ① Repeatedly verify the key point positions, and accurately calculate the required oil volume and additional amount.
② Before oil soaking, ensure proper circulation with high flow rates to maintain optimal drilling fluid performance, enabling efficient cuttings removal and guaranteeing downhole safety during the oil-soaking process.
③ When measuring the performance of the releasing agent, its density must match that of the drilling fluid.
④ Whether injecting with a mud pump or using two cement trucks for injection, it is essential to ensure consistent displacement and continuity throughout the pumping process, strictly preventing channeling that could compromise the soaking effect.
⑤ Pay close attention to recording the start and end times of the slurry injection, changes in pump pressure, variations in displacement, injected volume, volume of drilling fluid replacement, and whether any abnormalities occur throughout the process.
⑥ During the soaking period, the interval for displacing the drilling fluid depends on whether conditions downhole are normal—ranging from short to long. The amount of fluid displaced should be kept minimal rather than excessive, continuing until returns are observed at the wellhead (ensure the wellhead is fully filled before displacement begins).
⑦ Record the pressure during each jacking operation, the displacement volume, and the return conditions at the wellhead. If you notice an increase in pump pressure or no return at the wellhead, indicating a potential obstruction in the wellbore, promptly inject a snubbing agent to clear the blockage and restore circulation.
⑧ During soaking, periodically move the drill string up and down to help free any stuck components; when not moving, apply some of the suspended weight downward.
⑨ During the soaking period, the driller must remain at his post, closely monitoring the weight indicator to promptly detect any stuck conditions and prevent sudden, uncontrolled drilling motions.
⑩ After freeing the stuck pipe, start the pump with a small displacement and adjust the flow rate as needed. Once the pump pressure stabilizes, you can gradually increase the displacement. Use first gear to rotate the drill string at a low speed, avoiding any upward or downward movements of the drill string to prevent pump blockage. During the process of circulating the unblocking agent, never interrupt the circulation—this is crucial to prevent pump buildup and avoid causing the drill string to get stuck again.
58. After a malignant drill-through incident, how should it be handled correctly?
Answer: After a severe drill string jam, the cause should be immediately identified and addressed promptly.
① If the drill string has not fallen into the well, first attempt to restore circulation and move the drill string to prevent it from getting stuck.
② Thoroughly inspect the suspension system, braking system, and related air lines and transmission components, as well as the associated drilling tools and instruments. After resolving any issues on the surface, proceed with downhole operations.
③ If the drill string has not fallen into the well, you may slowly raise it. If there is no sticking, check the suspended weight and carefully inspect the drill string during retrieval.
④ If the drill string falls into the well, the situation will become complicated—especially when the drill pipe is particularly long. In such cases, it’s highly likely that the pipe will twist into large, tangled sections—or even break into several pieces altogether. At the same time, the exact position of the fish (the stuck object) remains unclear. Here’s what you should do: First, lower a bare drill pipe to locate the fish top. Carefully probe downward through the potentially affected wellbore section at a slow pace. Avoid descending too far to prevent pushing the fish top against the wellbore wall, which could further complicate the retrieval process. Second, once the fish top is identified, immediately attempt a make-up connection for retrieval. (If the fish top consists of a broken-off piece, be sure to record the precise depth before pulling out of the hole and switching to appropriate fishing tools.) When lifting the string back to the surface, take extra precautions to avoid getting stuck, and never use the rotary table to unscrew the connection. Finally, if the fish top cannot be located using this method, consider employing alternative techniques like electrical logging to pinpoint its position accurately, after which you can proceed with the retrieval operation.
59. Why can't the rotary table be used to unscrew the drill collar when retrieving drill strings and dropped objects?
Answer: The rotary swivel can easily fling away the retrieved fish or debris, complicating the situation further. Therefore, unless salvage efforts are definitively confirmed as failed, no chance should be taken—every remaining possibility must be pursued without resorting to the rotary swivel.
60. How to Properly Use a Magnetic Salvage Tool?
Answer: ① Select a suitable magnetic fishing tool based on the wellbore diameter; its maximum outer diameter should be 10–25 mm smaller than the wellbore.
② Locate actual samples of lost items, and test their magnetic strength and level of attachment.
③ Determine whether to use a pilot shoe based on the size of the dropped object.
④ Measure dimensions of each part, inspect threads and water holes, and sketch a diagram.
⑤ After running the drill string to the fish top, circulate and flush for 0.5 meters, then stop pumping and proceed with fishing operations. Ensure precise calculation and accurate measurement of the make-up length. Lower the fishing tool repeatedly in different directions, applying a weight of 5–10 kN—not too much—until the make-up length remains consistent across all orientations. Once this condition is met, you may pull out the drill string.
⑥ If multiple attempts fail to retrieve the object, it indicates that the item hasn’t been successfully lifted. In this case, gently rotate the reel and give it a slight nudge before trying again.
⑦If the dropped object is small, use a longer shoe; if the formation is relatively soft, you can start with a low flow rate, gently apply pressure while slowly rotating the drill bit to advance 3–5 cm, then stop pumping and drop a ball to retrieve the object.
⑧ Do not start the pump too abruptly to prevent knocking off the magnet.
61. How to Properly Use a Cava Fishing Jar?
Answer: ① Select an appropriate fishing jar based on the wellbore diameter and fish head size, and install a slip of the right dimension. If the fish top is deformed or has burrs, repair the fish head thoroughly before attempting retrieval.
② Remove the cylinder body, inspect and maintain all components, measure the dimensions carefully, sketch a diagram, and securely tighten the threads.
③ Circulate drilling fluid at least 0.5 meters above the fish head to flush away the accumulated sand around it.
④ Accurately calculate and precisely measure the salvage volume, then calibrate the weight indicator.
⑤ Stop the pump and lower the fishing tool. If resistance is encountered, gently apply pressure while slowly rotating, or lift and reorient the tool to retrieve it. This will allow the fish head to engage with the slips, lifting the drill string upward. If the suspended weight increases, it confirms that the downhole object has been successfully grabbed.
⑥ Before pulling out of the hole, fully circulate the drilling fluid by starting the pump, and then sharply brake twice after lifting the fish 1–2 meters off the bottom of the well. If the suspended weight does not decrease, it confirms that the fish is already stuck in the hole—only then should you proceed with pulling out of the hole.
⑦ After pulling out the drill string and removing the slip, gently lower the square drill pipe once, then use the elevators to rotate counterclockwise and back away.
⑧If the fish becomes stuck and circulation is blocked, lower the drill string and apply pressure of 200–500 kN to the fishing barrel (or use a down-the-hole hammer to deliver a downward impact), which will help release the slips from the fish. Then, rotate the string in the forward direction to disengage the fish from within the slips, allowing you to retrieve the entire fishing assembly.
62. How to Properly Use Positive-Thread Male and Female Cones for Fishing Drilling Tools?
Answer: Both the male and female cones come in two types—right-hand and left-hand threads—and the retrieval methods for male and female cones are essentially the same. The key difference lies in their applications: the male cone is suitable for retrieving tubulars with thicker walls, such as drill collars, drill pipe joints, or thickened sections, and it forms threads inside the tubular’s internal bore. In contrast, the female cone is used for retrieving tubulars with thinner walls, like the drill pipe body itself, and it creates threads on the outer surface of the tubular.
① Select the appropriate male and female cones based on the fish head water eye size and the outer diameter of the pipe body;
② Check whether the male and female taper threads are intact, and sketch a diagram indicating the dimensions.
③ Drill string assembly: male (female) taper + safety joint + drill pipe;
④ Drill down to 1-2 meters above the fish head, then start pumping and circulating to flush out the fish head. Mark the exact points on the square drill pipe where the fish head enters and where make-up connections begin.
⑤ Reduce the displacement and slowly lower the drill string to probe the fish head. Once the fish head is detected, determine whether you’ve entered the fish head by observing: if the suspended weight decreases while pump pressure rises, and you feel a slight pulling sensation when holding onto the square drill pipe—this indicates that you’ve successfully entered. However, if the pump pressure remains unchanged and the square drill pipe doesn’t move as expected, it means you haven’t yet penetrated the fish head.
⑥ Stop the pump and make up the connection. Taking the retrieval of a Φ127mm drill pipe using a male taper as an example, let’s illustrate the connection-making method: First, apply a pressure of 5–10 kN and rotate the tool twice to initiate the thread engagement. Carefully monitor the pointer gauge—when the suspended weight gradually increases, it indicates that the thread has started engaging properly. Then, steadily increase the pressure to 30–40 kN to fully complete the connection. For a 1:16 taper with 8 threads per inch, making 8 full turns (counting the number of engagement cycles) should suffice.
⑦ After confirming that the thread has been properly formed, lift the drill string and then lower it sharply twice, stopping just 2-3 meters above the well bottom. Only after verifying that the thread is securely set can you proceed with pulling out of hole.
⑧ When fishing for the fish head, you can rotate the drill string to probe from different directions. If you still can't locate the fish head, you should pull it out and then switch to a bent drill pipe to search for the fish head—never drill further blindly, as this could push the fish head deeper into the formation.
⑨ When retrieving and lifting the drill string, operations must be smooth—gently lift and lower—and it is strictly prohibited to use the rotary table to remove the drill collar.
⑩ After making the connection, if the lower drill string becomes stuck, first attempt to pump and circulate. If circulation is possible, inject a well-chosen foam-based releasing agent to free the stuck pipe. If circulation remains blocked, resort to reverse circulation combined with back-off operations to resolve the issue.
63. How to Properly Use a Milling Shoe?
Answer: ①Based on the shape of the dropped object and the wellbore size, select the appropriate type and specification of milling shoe. Generally, the outer diameter of the milling shoe should be 20–5 mm smaller than the wellbore diameter.
② Inspect the quality of the grinding shoe and create a sketch.
③ The drill string consists of: reaming shoe + drill collar + drill pipe.
④ When running the drill string, ensure the wellbore remains unobstructed; do not use a reaming shoe to scrape the hole.
⑤ Before grinding, thoroughly flush the bottom of the well. Then, stop the pump, lower the drill string while applying pressure (typically 30–50 kN), restart the pump, and begin low-speed milling and reaming.
⑥ During grinding and milling, it's common to lift the tool and make a quick pass every 30 minutes or so, then resume grinding.
⑦ If pump pressure rises while rotary torque decreases, it indicates that the milling shoe teeth have become worn flat—time to pull out of hole and replace the shoe. Alternatively, if you notice a significant reduction in iron filings within the cuttings, accompanied by a noticeable lightening of rotary drag, it means the dropped object has been completely milled away.
64. What causes the cable and instruments to get stuck during open-hole logging, and how should this be handled?
Answer: The reasons for logging tools getting stuck include:
① The cable remains stationary for a long time, causing it to stick and jam.
② Sand bridges or constricted formations can cause instruments to get stuck.
③ Deep wells, directional wells, and wells with irregular boreholes can cause instruments to get stuck due to the shoulder formation at the top.
④ During prolonged logging operations in the build-up, ramp-up, and highly deviated sections of directional wells—as well as in areas with significant total angle changes in straight wells—the cable becomes wedged into a protruding formation on one side, creating a keyseat. This results in progressively increasing resistance, ultimately leading to complete sticking.
Handling method: If the cable is only slightly stuck, gently pull it up and down within the safe tensile range to free it. However, if the cable is severely stuck or completely jammed, never attempt to forcibly pull it out—this could lead to cable breakage. Instead, use the core-pulling retrieval method to address the issue.
For wells where electrical logging encounters stuck conditions, a drill collar equipped with a central stabilizer can be used to ream and clean the hole, eliminating shoulder formations and breaking up keyways while reshaping the wellbore walls.
65. Briefly describe the procedures for unjamming a through-cable operation?
Answer: ① Secure the cable firmly with clamps, fixing it to the wellhead.
② Cut the cable from the ground. Attach a "mushroom head" to the cable end inside the well, and install a quick-connect fitting (compatible with the "mushroom head") to the cable end connected to the winch.
③ When running the drill string, lift the standpipe, connect the fishing jar securely at the bottom, and then thread the cable—equipped with a quick-connect fitting at one end—from the driller through the drill pipe’s inner bore down to mate with the "mushroom head" on the downhole cable. Once connected, tighten the cable using the electric winch, remove the clamps from the wellhead cable, and you’re ready to lower the drill string into the well.
④ After the first riser is seated on the rotary table, secure the cable connector to the drill pipe female joint using a dedicated pad. Then, disconnect the quick-connect joint, and have the driller thread the cable end from the winch down through the drill pipe’s water eye, connecting it to the "mushroom head" on the in-well cable. Once connected, tighten the cable with the electric logging winch, remove the clamp from the wellhead cable, and proceed to lower the next riser. Repeat this process continuously until the fishing tool successfully grabs the instrument.
⑤ Use an electric winch to pull the cable off the top of the instrument, retrieve the cable, and then raise the drill string to bring out the fishing jar and the instrument.
66. What are the procedures for retrieving cables, and what precautions should be taken?
Answer: If a cable breaks and falls into the well, you can use a retrieval tool to fish it out. Retrieval tools are divided into inner retrieval tools and outer retrieval tools. The operating procedures for both types of tools are identical. Here are the cable retrieval procedures and safety precautions:
(1) Salvage Operations
① Calculate the well depth at the cable break point when the cable inside the well snaps.
② During the first retrieval of the downhole drill string, after the rope catcher has been lowered to the depth of the broken wellbore, the lowering speed should be slowed down. If no resistance is detected, the string can be lowered an additional 150 meters beyond the bottom of the broken wellbore. Rotate the drill string one full turn, then slowly raise it by 1–2 meters before returning it to the original depth. Repeat this process—rotate again and carefully lift the drill string at a low speed. When disconnecting the drill pipe joints during retrieval, always use a lifting tongs to loosen the threads; never attempt to unscrew the joints manually or with hydraulic power tongs.
③ If the first attempt fails to retrieve it, each subsequent salvage operation can only increase the depth by 100 meters at a time—until the object is finally caught.
④ A small drill pipe can also be used instead of the Φ127 drill pipe to retrieve objects in a Φ216 wellbore; the depth can be determined based on the length of the small drill pipe.
(2) Safety Precautions
① When welding the external fishing tool with a male taper on-site, ensure that the hook opening of the tool is neither too large nor too small—typically about 15 mm larger than the cable’s outer diameter—and make sure the tool itself is approximately 1.5 to 2 mm long.
② Each time the fishing tool is lowered, the depth should not exceed 100 mm beyond the cable break point. Additionally, avoid over-rotating the rotary table (3–4 full turns) to prevent the cable from twisting into a large tangle, which could make it impossible to retrieve the drill string.
③ Each time the cable is retrieved, its total length must be accurately measured to provide a basis for the next retrieval.
67. How should the acoustic amplitude tool be handled if it gets stuck inside the casing?
Answer: Casing-internal acoustic amplitude logging tool sticking falls into two scenarios. In the first case, the tool can only be lowered but gets stuck at the top, making it impossible to retrieve. This typically occurs due to deformation at the male end of the casing. To address this, lift the tool back to the sticking point and assemble several people (whose combined weight is close to or exceeds the weight of the stuck cable) to alternately pull the cable up and down between the logging winch and the drilling platform. This motion will induce shaking and vibration in both the cable and the tool, potentially dislodging the stuck section above the obstruction. If this method proves ineffective, a small drill pipe can be used for through-the-casing retrieval, employing a slip-type fishing jar to extract the tool. In the second scenario, the tool becomes immobilized—stuck fast by cement chunks, sand accumulations, dropped objects, or other obstructions—preventing any upward or downward movement. In such cases, the direct through-the-casing retrieval method should be employed immediately. Hard pulling is strictly prohibited.
68. What precautions should be observed when operating the upper and lower vibrators?
Answer 1: Top Impact Tool
① Select the appropriate impact tool based on the condition of the stuck drill string.
② Calculate the lifting force based on the weight of the drill string above the sticking point and the load on the impact tool (lifting force = weight of the drill string above the impact tool + selected lifting force).
③ Before performing the jarring operation, inspect the safety of the suspension system and derrick. Remove the traveling block hook shackle and the automatic swivel attachment for the kelly, and securely fasten all remaining components with safety ropes. Additionally, install a stop bar on the crown block sheave to prevent the drill string from jumping out of its groove.
④ The weight indicator must be sensitive and reliable; prevent objects from falling down the well.
⑤ Once the fishing tool has hooked the downhole object, first lower the drill string to ensure the upper impactor is fully closed.
⑥ Lift the drill string to increase the tension to the calculated value, causing the drill column to elongate accordingly. At this point, lock the drum and wait for the impact. If the bit does not free up after the impact, lower the drill string slightly to ensure the impact tool fully closes and resets, then lift the drill string again for a second impact. Repeat this process multiple times until the bit is freed from sticking.
⑦ If the first impact cannot be generated, it may be due to insufficient lifting force. In this case, the drill string should be raised until the required tension is achieved (but never exceed the maximum lifting capacity of the drill string and the upper impact device within the well).
⑧ If a second impact cannot be generated, it may be because the upper striker hasn’t fully closed and reset. In this case, you should allow the drill string to descend further until it closes and resets completely.
⑨ The impact tensile force should be gradually increased from small to large, but must not exceed the maximum tensile force allowed by the upper striker.
⑩ In directional wells and complex wells, an accelerator can be connected to enhance the upward impact effect.
2. Down-the-Hole Hammer
① Select the appropriate down-the-hole hammer based on the condition of the stuck drill string.
② Calculate the square footage when the down-the-hole hammer is pulled up and closed, and mark a symbol on the square drill pipe.
③ Before jarring, inspect the safety of the suspension system and derrick. Remove the traveling block hook shackle and the air-powered tong, and securely fasten all remaining components with safety ropes. Additionally, install a stop bar on the crown block sheave to prevent the main hoisting rope from jumping out of its groove.
④This safety device must be sensitive and reliable; it should prevent objects from falling down the well.
⑤ After catching the fish, mark the top of the square drill pipe with an entry indicator.
⑥ Lift the drill string to fully retract the down-the-hole hammer (refer to the retraction mark marked on the square drill pipe), causing the drill string to elongate accordingly.
⑦ Slowly lower the drill string rapidly until the full lifting length is reached (i.e., the square entry after retrieving the dropped fish). Immediately apply the brake to the drum, generating a powerful downward impact from the down-the-hole hammer. Repeat this process of multiple shock impacts until the stuck pipe is freed.
⑧ When rapidly lowering after lifting as described above without fully releasing the lifting length, continuous vibrations occur, generating a certain upward impact force.
69. What precautions should be taken during milling operations?
Answer: Casing milling is an essential preparatory task for back-off operations. The following outlines the key operational procedures and safety precautions for casing-milling brake handle operation.
1. Preparatory Work
① The equipment has been properly maintained, and the drilling pump is supplying water smoothly.
② Select the appropriate milling shoe and milling tube size based on the wellbore conditions and the structure of the stuck object. Determine the length of the milling tube according to the wellbore quality and the depth of the fish head.
③ Calculate the fish top and mill shoe contact point for fish entry.
④ Lower the casing milling drill string (milling shoe + milling barrel + drill pipe) into the well.
2. Operating Instructions
① When milling shoes reach 1 meter above the fish top, start pumping to flush the area and record the suspended weight and pump pressure.
② Gradually lower the drill string while monitoring the shoe contact with the fish, and carefully probe for the fish top. Once the shoe touches the fish head, apply gentle braking, slightly engage the rotary table, and begin rotating the milling cylinder to engage the fish. After successful engagement, observe a slight increase in pump pressure. At this point, you can proceed with light pressure, slow rotation, and high displacement for the reaming operation. For a 216mm wellbore, use a drilling weight of 30–50 kN, a rotary table speed of 60–70 rpm, and a flow rate of 30 L/s.
③ During the reaming process, mill out half of a single pipe section, then slightly raise the drill string to ream the wellbore once. When lifting, be careful not to exceed the top of the fish.
④ After completing the casing run and preparing to connect the next drill pipe into the fish head, if you encounter resistance, apply slight additional pressure and use large tongs to gently rotate the drill string. At this point, if the square drill rod exhibits minor jerking motions but the weight indicator returns to the original suspended weight reading, and lowering the drill string encounters no further resistance while still allowing it to reach the desired depth for reaming, it indicates that the casing has been successfully engaged. You can then proceed with the reaming operation.
⑤ Each time reaming is completed, it should extend 2 meters beyond the single-rod female thread, serving as the "guide" for the next reaming operation.
3. Safety Technical Measures
① When the milling cutter encounters resistance during lowering into the well, do not attempt to ream—this could create a new hole. Instead, pull out the milling cutter, properly clean up the wellbore, and then lower it again.
② When inserting the milling shoe into the fish head, proceed slowly. If you encounter resistance, immediately stop lowering the shoe and instead apply intermittent rotational movements, carefully guiding it in from different directions. Alternatively, you can weld pins inside the milling shoe; by observing whether the fish head breaks the pins, you can confirm that the milling shoe has been successfully engaged with the fish head.
③ During reaming operations, if pump stalling occurs, immediately stop the reaming process. First, shut down the pump and release the return fluid; then, lift the drill string and select a clear wellbore section to restart the pump. Begin by circulating at a low flow rate, gradually increasing the displacement over time. Only after confirming normal circulation can reaming operations resume.
④ The first milling cylinder at the upper end of the milling shoe is most prone to damage and should be carefully inspected and rotated for use. Each milling cylinder should be replaced after 50 hours of operation.
⑤ When milling and retrieving the fish, if the fish tail is at the bottom of the well, it should be completely milled out. If the drill string is stuck in mid-air, lift out the milling barrel once you’ve milled within 1–2 meters of the fish tail, to prevent the fish from sliding further down.
70. What precautions should be taken when performing inverted operations?
Answer: The inverted operation and safety precautions are as follows:
1. Preparatory Work
① Prepare in one go a reverse-threaded drill pipe, reverse-threaded male cone, reverse-threaded safety joint, and wellhead tools—all with the same dimensions but greater strength than the downhole drill string.
② Conduct a thorough inspection of the equipment, paying special attention to the winch clutch and chains, and ensure accident pins are ready.
③ First, use a positive thread to reverse the connection, properly manage the drilling fluid, and then pull out the drill string. Attach the square drill pipe with a positive-negative threaded joint (with the positive thread coated in rosin) below, ensuring it’s securely tightened using double wire rope clamps. Next, weld three copper plates onto the connections. Finally, electrically weld three copper plates around all threaded joints between the square drill pipe and the center tube of the swivel. (If a reverse-thread tool is used, no additional copper plate welding will be required for the joint beneath the square drill pipe.)
④ Combined drilling tools (drill string configuration: reverse-threaded fishing jar, spear, male (or female) cone, etc. + reverse-threaded safety joint + reverse-rotation vibrator + reverse-threaded tool + reverse-threaded drill pipe).
2. Inverted Operation
① Drill down to 0.5 meters above the fish head, then start pumping for flushing. Secure the square slips and square Kelly bushing, adjust the weight indicator to ensure it’s sensitive and reliable, and finally engage reverse gear to prepare for making up the connection.
② Make a make-up connection (the make-up method is identical to that used for fishing with a male cone). After completing the make-up, switch to forward rotation, slowly raise the drill string until the tension slightly exceeds the weight of the fishing tool. Apply the brake firmly, then reverse the rotation, engage the rotary table clutch, and begin reversing the make-up connection.
③ During the reverse-rotation process, closely monitor changes in suspended weight and rotary table load. If the suspended weight decreases, the rotary table experiences minimal resistance, and rotation remains stable, it indicates that the fish has been successfully unscrewed. Conversely, if the suspended weight increases, this suggests that the stuck drill string is fully mobilized. In this case, immediately switch to forward rotation, start circulating the mud (adjusting flow rate gradually from low to high), and slowly raise and lower the drill string while avoiding any rotary table movement. Once the key is freed, you can proceed with pulling out of the hole. However, if the suspended weight continues to rise steadily and significant resistance persists, gently lower the drill string until the resistance subsides before attempting another reverse-rotation attempt. If the fish is tightly stuck and the rotary table clutch begins to slip, stop the main drive unit immediately. Then, use an emergency pin to lock the rotary table clutch in place, carefully controlling the main drive air switch to execute the reverse-rotation maneuver.
④ After knocking over and opening, switch to forward rotation to confirm the entry point. Then, simply pump to clear the water eye before pulling out the drill string.
3. Safety Precautions
① Downhole gauges, safety joints, and other tools must be accurately measured and sketched out.
② The down-the-hole drill string must be securely tightened with double tongs; making up the connection on the rotary table is strictly prohibited.
③ Before inverting, the square Kelly (except for the roller-type square Kelly) must be securely fastened with a wire rope. During the inversion process, personnel should retreat to a safe location, and any excess personnel must leave the rig floor immediately.
④ When reversing, the number of twisting cycles should be limited based on the drill string's steel grade and degree of wear.
⑤ Do not use the rotary table to break or remove drill collars during tripping operations.
⑥ Absolutely no using pliers teeth in place of the steel strips designed to prevent back-off.
71. What issues should be noted when running and reaming complex wells?
Answer: ①First, ensure underground safety with ground equipment, focusing on the drilling pump, swivel, high-pressure manifold, and cleaning systems. Additionally, the weight indicator must be sensitive and reliable.
②We must adhere to mid-course circulation, consolidating as we go. Properly manage and adjust the drilling fluid properties to ensure the formation of a stable wellbore wall.
③ During circulation, after stopping the pump, ensure that the drill string moves freely and can be fully lowered before connecting a single joint. When connecting the single joint, delay stopping the pump, speed up the connection process, and minimize the pump-off time as much as possible.
④ During the wellbore cleaning and reaming process, if equipment failure causes a prolonged inability to circulate, immediately pull out of the hole and make every effort to fully fill the well with drilling fluid.
⑤ If pump stalling occurs during reaming, immediately stop the pump. Raise the drill string to a clear wellbore section, continue rotating, and once the pump is restarted smoothly at low displacement, gradually increase the displacement to resume reaming.
⑦ When making a sidetrack, ensure that you avoid creating a new wellbore. Adhere to the method of "one flush, two passes, three sidetracks": After connecting the single joint and starting the pump for normal circulation, first flush the hole downward, then lift the drill string, rotate it to a new orientation, and flush again. Next, lift the drill string, rotate it, and sidetrack once more. If you encounter situations where flushing or circulating becomes impossible but sidetracking is absolutely necessary, employ the "jerk-and-sidetrack" technique: First, apply a pressure of 20–30 kN while rotating the rotary table, and closely monitor whether the gauge returns to zero. If no weight on bit is detected, immediately stop rotating the table. Then, reapply the same pressure of 20–30 kN and resume rotation—repeat this process until the sidetrack operation on the current single joint is complete. Finally, lift the drill string and sidetrack one more time. Never apply continuous pressure or continuously rotate the rotary table, as this could damage the equipment or compromise well control.
72. What precautions should be taken during reverse reaming operations?
Answer: ① Proceed with caution when reversing the drill string; securely fasten the safety rope to the drill pipe tongs to prevent them from swinging out and causing injury if the rotary table reverses unexpectedly.
② Carefully check the weight indicator, adjust the sensitivity meter to zero, and slowly raise the drill string until it reaches the sticking point. Then apply a tensile force of about 10 kN and immediately engage the brake on the drum.
③ Place the drill pipe slips into the wellhead to securely clamp the drill string, then slowly rotate the rotary table clockwise to begin reaming.
④ Once the rotary table load returns to normal, stop the rotary table, then lift the drill string and apply a tension of approximately 10 kN. Secure the drill pipe slips, re-engage the rotary table, and resume heavy-duty operation until the drill string is fully retrieved.
⑤ Make one cut, then lift slightly—don’t rush to finish, as this could cause the drill string to jam.
Chengdu Tdrill Energy Technology Co., Ltd.
Related News
The annual meeting of Chengdu Tdrill Energy Technology Co.,Ltd., themed "Leap into a New Journey, Achieve Success Today," has concluded successfully. All colleagues and guests gathered together to review past achievements, outline plans for the new year, recognize outstanding individuals, unite our strengths, and jointly embark on a new journey of high-quality development for the company.
2026 Spring Festival Holiday Notice
Our company is pleased to announce the 2026 Spring Festival holiday schedule: The holiday period will run from February 11, 2026 (the 22nd day of the 12th lunar month) to February 23, 2026 (the 7th day of the 1st lunar month). Normal office operations will resume on February 24, 2026 (the 8th day of the 1st lunar month). During the holiday period, routine business processing will be temporarily suspended. We will promptly respond to any inquiries or collaboration requests once we resume work. On this joyous occasion of the Spring Festival, our company extends festive greetings to all our valued customers. We deeply appreciate your long-term support and trust, and wish you a happy Spring Festival and smooth sailing in all your endeavors.
In oil drilling operations, the transition zone where the drill bit moves from soft rock formations into hard rock formations (or vice versa) is often a high-risk area for drill bit damage. A recent study, using sophisticated digital simulations, has revealed the underlying mechanical mechanisms behind this phenomenon and proposed effective solutions.