100 Questions About Drilling—Part One


Part One: Normal Operation Section

1. Why is it required to "stop the pump late and start it early" when rapidly advancing while connecting drill pipes?

Answer: Because during rapid drilling, the drilling speed is high and cuttings production is abundant. To overcome the poor suspension capacity of the drilling fluid and prevent sand settling and subsequent stuck pipe when making connections—especially since the fluid remains stationary for extended periods—we must "stop the pump late and start it early," thereby minimizing the time the drilling fluid spends at rest.

2. How to correctly determine if a roller bit is stuck?

Answer: If you encounter increased torque during drilling (e.g., higher rotary table load, periodic sticking and bouncing of the square drill pipe, intermittent tightness in the rotary table chain, fluctuating diesel engine noise, or the rotary table reversing unexpectedly after disengaging it), combined with a comprehensive assessment based on the bit's usage time and formation conditions, the drill bit's roller cones may be seized. In such cases, you should immediately initiate a circulation trip to pull out of hole.

3. What are the hazards of rapid drill pipe retrieval?

Answer: ① Easily causes the drilling rig to operate under excessive load;

② When complex conditions occur underground, it is easy to get the drill string stuck (bit balling);

③ Drilling out too quickly can lead to a blowout if the air release mechanism fails.

④ Easily generates significant suction pressure, leading to overflow, well kicks, or even formation collapse, thereby complicating an otherwise normal wellbore.

4. What are the hazards of drilling too quickly?

Answer: ① Can easily lead to abnormal wear of the brake band, brake drum, and hoisting rope.

②Once a sudden obstruction occurs, it can easily lead to accidents such as drill string breakage, stuck pipe incidents, or bottoming-out drilling.

③ Excessive formation pressure can easily lead to well leakage and wellbore collapse.

④ Causes the drill bit to collide with the wellbore wall, damaging the teeth and bearings, thereby reducing the drill bit's service life.

⑤ Easily allows large amounts of cuttings to enter the drill string through the drill bit nozzles, which can readily lead to pump-induced blockage of the drill bit nozzles.

5. What should be done if the brake fails when lowering the drill string?

Answer: First, firmly engage the low-speed clutch to slow down the descent. Then, personnel at the wellhead should quickly secure the slips or latch the elevator hook, and all workers should promptly move away from the wellhead.

6. What causes the wire rope to twist during drilling and pulling operations, and how should it be handled?

Answer: The reasons are:

(1) The new wire rope has not yet released its torsional stress;

(2) Severe rotation of drill string during tripping operations;

(3) The large hook pin has not been opened;

Handling method:

(1) Loosen the live end of the large rope and untwist the steel cable.

(2) Control the make-up and break-out speeds, and minimize drill string rotation;

(3) When the large hook pin is not yet open, you can secure the drill string with slips, then attempt to rotate the traveling block to release the brake pin and ease off the torque.

7. Why is the large hook pin opened during drill string make-up and break-out?

Answer: When running or pulling drill pipes, opening the hook pin primarily prevents the wire rope from twisting during make-up and break-out operations. This facilitates the rotation of the drill string when a centralizer is present in the wellbore, while also making it easier to handle tasks at the second platform and the wellhead.

8. Why is it sometimes necessary to circulate drilling fluid during the bottoming-out process?

Answer: This is because: ① The drilling fluid needs to be circulated for an extended period of time underground or before pulling out of the hole due to certain reasons, in order to prevent deterioration of the fluid properties or excessive sediment buildup that could lead to pump-starting difficulties; ② The underground formation may experience collapse; ③ Saltwater invasion or gypsum contamination can degrade the drilling fluid’s performance; ④ There may be minor losses downhole; ⑤ Downhole conditions are often complex, frequently resulting in pump-starting challenges; ⑥ When the open-hole section is long, the well is particularly deep, or there are high-pressure oil and gas formations present. To avoid worsening these situations, it is essential to circulate the drilling fluid periodically during the operation.

9. What causes drill string sticking, and how can it be prevented and addressed?

Answer: The reasons for encountering obstacles include:

(1) Pulling the drill string without replacing the piston or failing to properly refill the wellbore with drilling fluid can lead to well collapse;

(2) Poor drilling fluid performance leads to thick mud cakes and a narrow wellbore;

(3) The drill bit diameter is severely worn, and using a new drill bit afterward results in encountering resistance;

(4) Before pulling out the drill, ensure the drilling fluid is properly circulated—otherwise, cuttings won't be fully brought to the surface.

(5) Changes in drill string configuration;

(6) The wellbore is irregular, with sand bridges or dropped objects;

(7) After drilling through with a power drill for directional wells.

Prevention and Handling Measures: Before pulling out of the hole, properly manage the drilling fluid and ensure thorough circulation. During the process of pulling out, carefully maintain adequate fluid levels as specified. If any sticking occurs, reverse-rotate the drill string to free the bit. Before running in the hole again, thoroughly inspect the type and size of the drill bit, as well as any changes in the drill string configuration. While running in the hole, remain vigilant to avoid getting stuck. When pulling out of the hole, avoid forcefully extracting the drill string if you notice a "piston effect." Similarly, if encountering resistance while running in, never apply excessive pressure—instead, carefully ream the hole to resolve the issue.

10. When drilling into formations below the Dongying Group and encountering resistance, what precautions should be taken during reaming?

Answer: (1) Strictly adhere to the principle of "one flush, two circulations, three reaming," and strictly prohibit applying pressure while rotating and lowering the drill string, to prevent creating a new wellbore.

(2) Closely monitor changes in pump pressure to prevent pump stalling. Gradually increase the pump displacement from low to high.

(3) Properly manage the drilling fluid, and once circulation returns to normal, increase the flow rate for well cleaning.

(4) Repeatedly ream through the complex wellbore sections until there is no obstruction.

11. When drilling encounters resistance and scrapes while penetrating the upper soft formation, what issues should be noted?

Answer: (1) If you encounter resistance while drilling through the upper strata, pull out the drill bit, replace it with a male cone, and then run drill pipes to ream and clean the wellbore.

(2) Maintain the drilling fluid with good flowability and sand-carrying capacity;

(3) Focus primarily on toning and unblocking, with gentle pulling and stroking as appropriate;

(4) Power drilling tools are strictly prohibited from skidding.

12. Why doesn’t the pump turn on after drilling is completed? How should this be handled?

Answer: The reasons are:

(1) There is debris inside the drill string, or something falls into the drill bit's water jets during drilling operations, causing blockage;

(2) During the drill-down process, if the lowering speed is too fast, cuttings from the drilling fluid may enter the drill string; alternatively, wellbore collapse could lead to severe backflow, causing cuttings to get lodged inside the drill string and block the bit nozzles.

(3) The wellbore mud cake is thick and heavily coated with rock cuttings, which squeeze into the drill bit during drilling, blocking the water jets.

(4) Ground pipelines or drilling equipment freezing during winter;

(5) The drill string filter is clogged with debris;

(6) Thick mud cake on the wellbore wall or wellbore collapse causes blockage in the annulus, preventing the drilling fluid from returning upward.

(7) While drilling downward, encountering resistance caused by hard pressure or multiple strings failing to return drilling fluid—resulting in the drill bit becoming embedded in cuttings and preventing pump circulation.

Handling: Before deciding whether to start the pump or not, first eliminate any surface-related factors. Then, address any downhole blockages. If the drill bit nozzles are clogged, vigorously move the drill string up and down to use surging pressure and clear the nozzles. If this approach proves ineffective, pull out of the hole to clean the nozzles directly. If the annulus is blocked, repeatedly move the drill string up and down to break through the obstruction, then gradually increase the pump rate while carefully monitoring the situation. If clearing the annulus still fails, pull out of the hole entirely until reaching a clear section before restarting the pump—and only then proceed with drilling downward. If you detect formation fluid influx or loss during the process, immediately pull out of the hole completely, ensuring you finish the operation without restarting the pump at any point. This precaution is critical to prevent formation collapse, which could lead to stuck pipe incidents.

13. What causes the pump pressure to rise during drilling, and how should it be handled?

Answer: The reasons include: wellbore collapse, blockage of the drill string's water jets, excessive cuttings accumulating and piling up in the narrow annulus, changes in drilling fluid properties, blunting or blade loss of the scraper bit, and uneven drilling fluid density.

Treatment methods: If wellbore collapse occurs, circulate drilling fluid at a high displacement rate, repeatedly ream the hole to remove cuttings, and then resume drilling gradually under light pressure until normal circulation is restored. If drill string accumulates with rock debris, eliminate the buildup by rotating or moving the drill string up and down. If pump pressure continues to rise, stop pumping temporarily and agitate the drill string to break up the accumulated debris before restarting the pump to flush it out. If drilling fluid performance deteriorates, halt drilling operations for proper treatment. For uneven density, supplement barite in segmented sections or use one pump to circulate while another pump mixes the fluid at low pressure until uniformity is achieved.

14. What causes the pump pressure to drop during drilling? How should it be checked? And how should it be addressed?

Answer: Reasons for the drop in pump pressure include poor water supply to the pump, leaks in pipelines or valves, damage to drill collars causing short-circuit circulation, damaged or lost nozzles at the drill bit, broken drill pipes, well kicks, and gas invasion leading to foaming of the drilling fluid, among others.

Inspection method: First, check the ground, pump operation, and pipelines. Next, examine whether the gate has any pinholes or short-circuiting circulation, verify the accuracy of the pressure gauge, and then assess whether the downhole drill string is punctured or broken, if the nozzles are damaged or detached, and whether well leakage has occurred.

Handling measures: For surface-related issues, organize emergency repairs and address drilling fluid foaming. If downhole drill tools or nozzles become damaged or punctured, immediately pull out the drill string and thoroughly inspect the tools. During the retrieval process, avoid using the rotary table to unscrew connections, and refrain from sudden braking to prevent the drill string from coming loose or breaking off. In case of a well kick, promptly resume continuous circulation of drilling fluid while pulling out the drill string.

15. During drilling, if the rotary table load increases and you disengage the rotary table clutch to shift into reverse—what’s the reason behind this? And how should it be handled?

Answer: Reason:

(1) Formation collapse and cuttings fall (e.g., when drilling into faults, fractures, or fractured formation zones, etc.);

(2) Drill bit dry drilling or mud packing;

(3) Drill bit gear wheel seized or scraper blade broken;

(4) Downhole dropped objects;

(5) Short-circuit circulation prevents cuttings from being brought out;

(6) The wellbore trajectory of the directional well is poor, with high inclination, significant displacement, and severe dogleg severity.

Handling: First, determine whether the drill bit is functioning properly. If dry drilling occurs, lift the drill string and repeatedly scrape the wellbore to clear any blockages. Alternatively, gently rotate the string to assess the condition of the drill bit. If a short-circuit circulation is detected, immediately pull out the drill string for inspection. Based on formation forecasts, data from nearby wells, and analysis of returned cuttings, identify the location and extent of wellbore collapse, then implement effective measures to address the issue and prevent sticking. If the wellbore trajectory is problematic, consider simplifying the drill string configuration to reduce torque.

16. What causes bouncing during drilling, and how should it be handled?

Answer: Jumping drill typically occurs during the drilling process with a roller cone bit, and the reasons include:

(1) Encountering alternating layers of soft and hard gravel, along with heterogeneous limestone formations.

(2) Well collapse or objects falling down the well.

(3) Excessive torque when using a large-tooth drill bit.

Treatment method: Adjust parameters to eliminate bit sticking, and make a comprehensive assessment based on formation lithology. If the treatment proves ineffective, consider the possibility of downhole debris. Pull out the drill string to inspect the bit for wear, and take immediate, effective measures. During the process, ensure careful prevention of bit sticking.

17. What causes bit sticking during drilling, and how should it be handled?

Answer: (1) The scraper drill bit encounters alternating soft and hard layers in the formation;

(2) Excessive drilling pressure or bit sticking with the scraper drill bit;

(3) Drilling through gravel layers or limestone solution caves;

(4) Formation spalling or objects falling into the wellbore;

(5) Roller bit mud packing or roller bit seizure;

(6) Drop the tooth wheel or scraper blade;

(7) After the scraper drill bit diameter is reduced, it becomes smaller than the stabilizer diameter.

Handling: If the formation issue can be resolved by adjusting the drilling pressure and rotation speed, proceed accordingly. If this approach proves ineffective, it may be caused by the drill bit or dropped objects—promptly pull out the drill string for inspection to determine the next course of action.

18. What should be done if the transmission chain breaks during drilling?

Answer: (1) First, we must maintain circulation;

(2) When the well is shallow, use manual labor to rotate the square drill pipe or operate the drawworks chain with an air hoist to move the drilling tools;

(3) When drilling to great depths, apply part or all of the drill string's weight downward, causing the drill string to bend and reducing the likelihood of getting stuck.

(4) Quickly organize personnel to reconnect the drill string, then lift the drill assembly, inspect each component for proper function, and resume drilling.

19. What causes the water hose to wrap around the square drill pipe during drilling, and how can it be handled?

Answer: The reasons include issues with the faucet bearing (e.g., damage, lack of grease), overly tight packing on the flushing tube, bending of the square drill pipe causing abrupt rotation when starting the rotary table, failure to secure the faucet with an anti-torque cable as required, and the absence of a locked safety pin on the traveling block.

After wrapping the water hose around the square drill pipe, use a power tong to rotate the pipe; if the wrapping is severe, remove the kelly or the square drill pipe altogether. If the swivel packing gland is too tight and slightly wraps around the square drill pipe, secure the swivel with a rope clamp and slowly rotate it for a short period.

20. Why does the pointer weight drop during drilling, and how should it be handled?

Answer: The reasons are either the bit becoming damaged or the drill string breaking.

Handling procedure: First, lift the drill string to inspect the weight indicator sensor, pressure transmission lines, and check for oil leaks in the gauge itself or at the connections, as well as any signs of component damage. If no leaks or damage are found, recalibrate the weight indicator immediately. If the weight indicator is intact, promptly pull out the drill string for a thorough inspection and decide on the appropriate course of action based on the findings.

21. Why does the drill bit become mud-packed? What are the symptoms? How should it be handled?

Answer: The reasons are:

(1) Dry Drilling

(2) The drill bit selection is incompatible with the formation—when drilling into soft clay layers, the penetration rate is high while the flow rate remains low.

(3) The drilling fluid has poor performance, with high viscosity and high yield stress.

Phenomenon: After the mud packs around the drill bit, symptoms such as bit balling, stick-slip vibration, reduced drilling speed, increased rotary table load, elevated pump pressure, and sticking or piston-pulling issues with the drill string may occur.

Action: After detecting a bit balling, first address the drilling fluid to ensure it maintains good flowability. Frequently scrape the wellbore or perform high-speed reaming, apply light weight-on-bit during drilling, and increase the displacement rate. If these measures prove ineffective, immediately pull out of the hole—doing so at a slow pace to prevent piston action. If necessary, connect the square drill pipe for circulation and reverse reaming before fully pulling out of the hole. During the trip-out process, if drilling fluid cannot be properly circulated or pumped back into the well, temporarily disconnect and reconnect the square drill pipe while circulating or injecting fluid in stages. This helps avoid collapsing the wellbore walls. Under no circumstances should you attempt a hard pull if stuck—always prioritize preventing stuck pipe incidents.

22. Why is it especially important to securely clamp with both pliers when using a scraper drill bit?

Answer: When the scraper drill bit penetrates, the torque fluctuates—sometimes high, sometimes low. If the connection isn’t tightened properly, the high torque will cause it to automatically tighten. In cases of severe sticking, this can lead to the drill pipe threads being over-tightened or even stripped and falling into the wellbore.

The torsional strength of the connection is related to the torque applied during make-up. If the make-up torque is increased during connection, the thread joint can withstand greater torque during drilling without relative slippage between the threads. Therefore, when using a scraper bit, securely tightening the connection with both tongs ensures: 1) prevention of over-torque, 2) easier disconnection during trip-out operations, and 3) protection against reverse torque causing excessive loosening, cross-threading, or short-circuit circulation.

23. Why can't the turntable be started under pressure?

Answer: Due to the drill bit's cutting edge penetrating the formation under pressure, initiating the rotary table generates high torque, which can easily damage the drill bit, twist and break down drilling tools, and even harm components like clutches and chains. Moreover, excessive load may also cause damage to the rotary table, drawworks, and power machinery. Therefore, it is not advisable to apply pressure when starting the rotary table.

24. What principles should be followed during core drilling?

Answer: Gently apply pressure and slowly rotate the turntable to carefully begin core drilling, gradually increasing the drilling pressure from low to high. Ensure even feed of the drill bit and incrementally boost pressure to prevent bit slippage. In soft formations, closely monitor for core blockages and manage any instances of stuck pipe. Maintain an appropriate drilling speed that matches the applied pressure—when drilling speed slows down, identify the cause promptly. Avoid applying excessive pressure, and continuously analyze the formation being drilled. Finally, decisively select the right formation, cut the core, and pull out the drill string.

25. What precautions should be taken when pulling the core and drilling?

Answer: (1) Operate smoothly—lift gently and lower slowly;

(2) When removing the swivel shackle, do not rotate the rotary table;

(3) Continuously fill the drilling fluid;

(4) The brake lever should be operated by skilled personnel.

26. Why shouldn't you use the core barrel to ream the hole when encountering resistance during core drilling?

Answer: If core barrels are used to ream the wellbore, it can cause deformation or curling of the core claws, leading to situations where the core fails to enter the core barrel during retrieval, resulting in core damage and reducing the core recovery rate. In soft formations, reaming with core barrels may even create new boreholes. Moreover, due to the relatively large diameter of the core barrel, reaming can easily lead to pump stalling. Typically, core barrels are made from thick-walled casing pipes, making them prone to bending or even breaking under the stress of reaming operations.

27. Why does wellbore collapse occur? What are the associated phenomena? How should it be handled?

Answer: The reasons for well collapse include:

① The excessive fluctuating pressure caused by the up-and-down movement of the drill string leads to an imbalance in stress on the wellbore wall;

② Drilling fluid was not promptly pumped back in after pulling out of the hole, causing a drop in hydrostatic pressure;

③ The drilling fluid has too low density, leading to high fluid loss and poor mud cake quality, which fails to effectively control the water absorption and swelling of shale, resulting in wellbore instability.

④ Drilling fluid performance changes too drastically, making the wellbore unstable;

⑤ Loose and poorly cemented formations, fractured strata, quicksand layers, and alternating gravel and clay beds are prone to wellbore collapse when exposed to drilling fluid infiltration.

⑥ Well kicks and well leaks lead to well collapses;

⑦ Drilling fluid return velocity is too high.

Phenomenon:

① While drilling, the drill suddenly binds or even stops rotating altogether, while pump pressure rises or pumping becomes blocked and suspended weight decreases;

② During drill string retrieval, the drilling fluid flows back, resulting in sticking when lifting and encountering resistance when lowering.

③ During circulation, a large amount of cuttings and loose fragments return to the surface, and their volume doesn’t decrease even after prolonged circulation.

Handling Method:

① Maintain and restore circulation as much as possible, vigorously circulate the drill string, adjust drilling fluid properties to stabilize the wellbore, and effectively remove cuttings.

② In loosely consolidated formations where wellbore collapse occurs, if circulation can be maintained, drill fluid should be treated and circulated simultaneously to carry away cuttings and stabilize the wellbore walls. However, if pump pressure builds up excessively—indicating a potential loss of circulation—do not forcibly restart the pump, as this could lead to formation fracturing and subsequent stuck pipe. Instead, immediately initiate an emergency trip, continuously circulating and replenishing the drill fluid as you pull the drill string out of the hole.

③ After pulling out the drill string, prepare an adequate volume of high-performance drilling fluid, then carefully run the drill bit back into the wellbore to check for obstructions. Ensure you prevent pump pressure buildup or sticking, and continue until the wellbore is fully clear and the well walls are stabilized—only then should you resume drilling.

28. Why is it necessary to circulate drilling fluid before pulling out of the hole?

Answer: ① To remove all cuttings from the wellbore and maintain well cleanliness, properly adjust the drilling fluid properties to ensure safe and smooth tripping operations.

② For special operations such as electrical logging or pulling the drill string before running the casing, ensure thorough circulation to guarantee smooth well logging and successful cementing during casing installation.

③ When drilling into high-pressure oil and gas formations, to prevent well kicks, thoroughly circulate and properly adjust the drilling fluid properties before pulling out of the hole.

29. Under what circumstances should a siphon inclinometer or suspended well inclination measurement not be used?

Answer: ① The drilling fluid performance is poor.

② Suspended weight is incorrect.

③ The alignment is incorrect.

④ The underground conditions are complex.

⑤ Pump pressure is dropping.

30. Why is it necessary to circulate drilling fluid when pulling out of the hole? How should it be done properly? And what if it can’t be circulated effectively?

Answer: After pulling out part of the drill string, the fluid level inside the well will drop. To maintain hydrostatic pressure balance, it is essential to promptly pump drilling fluid into the well, preventing formation fluids from entering due to the reduced hydrostatic pressure. Meanwhile, in loose formations, the dropping fluid level may trigger wellbore collapse.

To properly circulate the drilling fluid, it is essential to assign specific responsibilities and have dedicated personnel conduct regular inspections. Typically, the fluid should be pumped in each time a standpipe is lifted; however, the process isn’t complete until the liquid level in the mud tank drops and mud returns visibly at the wellhead, indicating that the system is fully filled. In cases involving high-pressure oil, gas, or water formations—or when starting the first round of drilling—the drilling fluid must be continuously topped up to ensure adequate circulation at all times.

If the displacement volume is less than the volume of the drill pipe being pulled out, or if the mud level in the well does not drop, the cause must be identified immediately. First, check whether the surface lines are blocked and whether the valves are fully open. If there are no issues on the surface, observe whether the fluid level inside the well is decreasing. If you notice a "piston effect," lower the drill bit to a clear section of the wellbore and circulate to flush the well walls thoroughly. If the bit becomes encased in mud and cannot be freed, connect the square drill pipe and continue circulating drilling fluid. In case of any overflow downhole, follow the prescribed well-control procedures for managing the situation.

31. What causes the sudden reverse flow or wellbore fluid surge inside the drill pipe during tripping out? And how should it be handled?

Answer: Reason:

① Drilling fluid density is uneven, or wellbore collapse occurs due to inadequate filling of the drilling fluid.

② Premonitions before a blowout.

Handling procedure: Under normal circumstances, drilling should be stopped immediately, the square drill pipe connected to control the kick, and the annulus filled with drilling fluid. Depending on the situation, the drill string can then be moved slightly before slowly starting the pump to resume circulation at normal rates. Once circulation is restored, stop the pump, remove the square drill pipe, ensure no further influx of drilling fluid occurs, and proceed with the next drilling operation. However, if severe oil or gas influx is detected during circulation, preparations for well-killing operations should be promptly initiated. If the pump cannot be started to circulate the fluid, the drill string must be pulled out immediately, while simultaneously ensuring the annulus is properly filled with drilling fluid, to prevent serious wellbore collapse that could lead to stuck pipe.

32. What causes sticking during drill-out operations, and how should it be handled?

Answer: Reason:

① Well collapse, sand bridge;

② Objects falling into the well;

③ Wellbore diameter reduction or drill bit mud packing;

④ The wellbore has a keyway.

Handling method:

① Regardless of the cause of the stuck condition, do not attempt to force or pull forcefully. Instead, drill downward to a clear section, connect the square drill pipe, start pumping to circulate the fluid, move the drill string up and down, analyze the situation, accurately determine the cause of the sticking, and then develop appropriate technical measures.

② If there are objects fallen into the well, they can be handled by rotating while lowering them.

③ If there are objects fallen into the well, they can be handled by rotating while lowering.

④ For necking and mud packing, use high-displacement flushing, combined with high-speed rotation of the drill string or reverse reaming to address the issue.

⑤ If the keyseat gets stuck, gently lift and slowly rotate it while carefully backing off to free it.

33. The low-speed airbag broke during the drill-out process—how should it be handled correctly?

Answer: ①If there isn’t much downhole drilling equipment, you can insert an emergency pin into the low-speed clutch to control the overall lifting of the drill string, then finish with high-speed lifting before replacing the air bag. During high-speed lifting, a supervisor must be present on-site to monitor the wellbore conditions, ensuring smooth and normal operations, and strictly preventing any potential stuck-pipe incidents.

③ If there are many downhole drill strings, insert the safety pin, connect the top drill pipe, start pumping to circulate the drilling fluid, lift the drill string high, and periodically lower and move it up and down. At the same time, organize personnel to quickly replace the low-speed air bag.

34. If the air release valve fails during drill string retrieval, what emergency measures should be taken?

Answer: If the low-speed air release valve fails during drill string retrieval, immediately disengage the main clutch. Before the rig comes to a complete stop, step on the anti-collision derrick hammer again while simultaneously applying emergency brakes using the brake lever. Then, inspect, repair, or replace the air release valve as needed. Periodically lower and move the drill string up and down, or rotate the rotary table to keep the string in motion. If replacing the valve takes an extended period, try connecting the square drill pipe to circulate drilling fluid and continue moving the drill string. Ideally, remove an air release valve from another location and install it as a temporary fix.

35. During drill string retrieval, improper operation has already caused the drill pipe to be lifted by a single lifting lug. How should this situation be properly handled?

Answer: Immediately apply the brakes—do not allow the elevator to sit on the rotary table. First, securely clamp the drill pipe slips, then gently rotate the rotary table to prevent sticking. Afterward, proceed with further actions based on the specific situation.

① If the drill string weighs relatively little and the drill pipe is not severely bent, you can hook up the lifting lug and slowly raise it to remove this single joint. When lifting, make sure the slips do not come off the rotary table—just in case.

② If the drill pipe is severely bent, you can connect another single drill pipe section to the bent one and carefully pull it out and remove it.

③ If the bend is severe and the drill string is heavy, you can cut off the bent section, use a fishing tool to retrieve it, and then replace the damaged drill pipe.

If the drill pipe breaks, select the appropriate fishing tool based on the condition of the fracture. If the fracture is relatively smooth and even, you can use either a slip-type fishing jar or a female cone. However, if the fracture is severely torn and deformed, first repair the fish head before attempting to retrieve the pipe—never use a male cone to artificially damage the fish head.

36. What precautions should be taken when pulling up a scraper drill bit?

Answer: First, properly adjust and stabilize the drilling fluid properties, ensuring thorough removal of drill cuttings to meet the requirements for pulling out the drill string. Since multiple centralizers are used, sticking or getting stuck is more likely, so always proceed with low-speed retrieval in first gear. Pay close attention to the weight indicator—if resistance or sticking occurs, avoid excessive lifting or forceful pulling. Never exceed one-third of the current suspended weight; instead, gently reciprocate the drill string up and down or reverse circulation to free it gradually. Before fully pulling out the drill string, ensure proper filling of the wellbore with drilling fluid and monitor carefully for any "piston effect." While the drill string remains stationary, actively rotate the rotary table to keep the drill string moving, preventing it from seizing due to sticking. If you encounter a stuck condition during retrieval and need to start pumping circulation, make sure to lower the drill string into an unobstructed, clear section before activating the pump.

37. What is "pulling the drill string with the piston"? What are the associated hazards, and how should it be handled?

Answer: Due to poor drilling fluid performance, wellbore shrinkage occurs, causing the drill bit or stabilizer to become mud-packed. This leads to continuous sticking during tripping operations, with the drilling fluid rising upward along with the drill string, resulting in an empty drill pipe and making it difficult to unscrew the kelly at the rotary table. In severe cases, reverse circulation becomes pronounced—this phenomenon is referred to as "tripping and pulling the piston."

Its main hazards are: first, pulling out of the wellbore can lead to downhole complications; second, it may cause drill collars to get stuck, disrupting circulation and resulting in severe stuck-drill incidents; and third, it can trigger suction-induced well kicks.

The handling method is:

① Once the "piston-pulling" phenomenon is detected, immediately stop pulling the drill string. Lower it into the clear section, start pumping to circulate the drilling fluid, adjust its properties, and then vigorously move the drill string up and down while flushing the wellbore walls. Additionally, intermittently engage the rotary table to rapidly swing the drill string back and forth, helping to break free any mud packs. After confirming that the drilling fluid performance has improved, proceed with retrieving the difficult section at low speed using first gear—or reverse-drill if necessary.

② If the piston-pulling phenomenon is severe—making it impossible to lower or pump through—the drill string should be immediately pulled out of the hole forcefully. After retrieving every 3 to 5 stands, connect a square drill pipe and continuously circulate drilling fluid down the drill pipe until the entire string is retrieved.

38. Why can't you immediately pull out the drill or take a survey after adding weight?

Answer: Because the barite powder, after weighting, has not fully hydrated, leading to a higher amount of barite adhering to the wellbore walls and resulting in a greater coefficient of friction, sticking is more likely to occur. Therefore, drilling should not be immediately stopped or inclination measured after weighting; instead, thorough circulation is required before proceeding with drilling or inclination surveys.

39. What are the features of the H-series (formerly J-series) drill bits produced by Jianghan Drill Bit Factory? What are the key operating parameters of the H517 (J22) drill bit?

Answer: The "H" series drill bits produced by Jianghan Drill Bit Factory correspond to the "J" series drill bits from Hughes Corporation of the United States—specifically, steel-toothed drill bits H116–H346 match J1–J8, while carbide-tipped drill bits H437–H837 align with J11–J99.

Its main features are:

(1) Sliding seal bearings, which utilize either rubber-ring sealing or metal sealing, boast a longer service life compared to other types of bearings.

(2) Gauge protection: This series of button-bit and some carbide-tipped bits feature gauge protection, helping to minimize diameter wear during drilling.

(3) Jetting, paired with medium-length, extended, and pulse nozzles, can fully leverage the jetting effect, significantly enhancing the hydraulic rock-breaking capability.

The main operating parameters for the H517 (J22) drill bit are: rotational speed of 45–100 rpm, and drilling pressure ranging from 108 to 194 kN. Note: The maximum drilling pressure cannot be used simultaneously with the highest rotational speed.

40. What should you do if the water hose or faucet suddenly breaks during drilling, making it impossible to circulate the drilling fluid?

Answer: During drilling, if the faucet leaks drilling fluid or the hose is damaged, repairs or replacements should be carried out while simultaneously pulling the drill string. If downhole conditions are complex or replacement takes a long time, the drill string should be pulled up into the technical casing; if no technical casing is available, the entire drill string must be retrieved completely. Under no circumstances should the square drill pipe be used to leave the drill string in the well for repairing the faucet or replacing the hose, to prevent the drill string from getting stuck.

41. What causes reduced or no return of drilling fluid at the wellhead during drilling, and how should it be handled?

Answer: First, check whether the surface circulation system and mud pump are functioning properly. If the surface equipment is normal, the issue likely lies in downhole losses, which could be caused by:

① Subsurface permeable loss zones or formation fractures.

② There are limestone caves.

③ Well collapse causes formation fluid loss.

Handling method:

① Permeability loss: For inflow and outflow rates where the leakage exceeds but remains below 5 cubic meters per hour, you can address the issue by increasing drilling fluid viscosity while reducing its density, as well as by lowering the pump rate and allowing the drill string to remain stationary during tripping operations.

② If the loss exceeds 5 cubic meters per hour or if a severe loss occurs, immediately organize a trip out of the hole and continuously circulate drilling fluid. After pulling out of the hole, implement wellbore sealing measures.

③ If wellbore collapse or fluid loss occurs, first reduce the flow rate to maintain circulation, adjust the drilling fluid properties accordingly, thoroughly circulate the drill string to remove cuttings, and immediately halt drilling. Once the situation stabilizes, resume drilling while closely monitoring for any potential sticking issues.

42. What is a short-circuit loop? What causes it? How can it be identified? And how should it be handled?

Answer: When drilling fluid doesn’t return entirely through the drill bit nozzles, it’s called a short circuit.

The causes of short circuits include downhole drill string damage, reverse connections, disconnections, and breakages.

The phenomenon of short-circuiting manifests as a drop in pump pressure, while pump displacement remains unchanged. As a result, cuttings from the lower formation cannot be effectively carried upward, leading to an accumulation of cuttings in the upper formations. After short-circuiting occurs, it can cause issues such as bit balling, sticking, and erratic drilling behavior, including slower penetration rates—and in severe cases, even getting the drill string stuck. Additionally, if the drill string becomes disconnected, breaks off, or experiences a significant drop in pump pressure, you may notice a corresponding decrease in rotary table load, making the operation feel lighter.

If the surface is normal, immediately organize a slow and steady drill string retrieval. Avoid using the rotary table to unscrew the connection, and have both inner and outer riggers thoroughly inspect the drill string. At all times, remain vigilant for any signs of sticking during the retrieval process, and prevent sudden lifting or braking that could lead to drill string-related incidents.

43. Why is it necessary to pump drilling fluid as specified during the casing running process?

Answer: The main purpose is to balance the pressure difference between the inside and outside of the casing, thereby achieving:

(1) Prevent the check valve from being damaged due to excessive back pressure.

(2) Prevent the casing from being squeezed and damaged due to excessive hollowing out.

(3) Maintain sufficient suspended weight to ensure smooth casing running.

44. What precautions should be taken when displacing drilling fluid with cement slurry?

Answer: (1) All parties actively cooperate to ensure the continuity of work;

(2) Properly manage the disposal of drilling fluids to prevent environmental pollution;

(3) Ensure the drill floor, engine room, and pump room are well coordinated and working in harmony to prevent operational errors;

(4) As the drilling fluid is started, all personnel evacuate the pump room and the circulation system, leaving only a few people on the drill floor while the rest take shelter in a safe area.

45. What should be noted when starting pump circulation after the casing has been run?

Answer: ① First, fill the casing with drilling fluid and coordinate properly with the pump room operators—mistakes must be avoided.

② Start the pump with flow rate increasing gradually; never abruptly open the pump at high flow rates, as this could lead to cuttings blockage, causing pump pressure buildup or even wellbore leakage.

③ Closely monitor changes in pump pressure. If any unusual situation arises, address it promptly—never stop the pump without authorization.

④ Avoid adding excessive water or performing drastic treatments on the drilling fluid to prevent wellbore collapse.

46. Why can't you weld the casing?

Answer: ① Electro-welded casing is prone to altering the material's microstructure, thereby reducing its strength;

② Easily leads to stress concentration zones, creating fatigue sources and increasing the likelihood of fracture;

③ Welding quality cannot be guaranteed, easily leading to casing falling into the well accident.

47. Why is it necessary to weld the wellhead before cementing or installing a wellhead seal and then allowing the cement to set under pressure?

Answer: Before cementing high-pressure oil and gas wells, the drilling fluid density is relatively high to stabilize the oil and gas formation. However, after cementing, as the cement slurry begins to set, a weight loss occurs, reducing the hydrostatic pressure in the annular space. This imbalance can no longer counteract the formation pressure, allowing high-pressure oil and gas to flow into the annulus, leading to: ① The incompletely set cement slurry continues to flow, causing channeling of oil and gas and compromising the integrity of the cement job. ② Drilling fluid continuously overflows at the wellhead, making it impossible to properly seal the wellhead and potentially resulting in a blowout after cementing. To address these issues—specifically the weight loss of the cement slurry and the risk of formation fluids leaking out—high-pressure oil and gas wells typically employ one of two strategies: either welding the wellhead first before cementing, or using a wellbore packer to maintain pressure during the waiting period for cement to set.

Chengdu Tdrill Energy Technology Co., Ltd.

Related News


A New Journey, Achieving Success Today|The annual gala of Chengdu Tdrill Energy Technology Co.,Ltd. concludes successfully, setting sail on a new chapter with renewed vigor.

The annual meeting of Chengdu Tdrill Energy Technology Co.,Ltd., themed "Leap into a New Journey, Achieve Success Today," has concluded successfully. All colleagues and guests gathered together to review past achievements, outline plans for the new year, recognize outstanding individuals, unite our strengths, and jointly embark on a new journey of high-quality development for the company.


2026 Spring Festival Holiday Notice

Our company is pleased to announce the 2026 Spring Festival holiday schedule: The holiday period will run from February 11, 2026 (the 22nd day of the 12th lunar month) to February 23, 2026 (the 7th day of the 1st lunar month). Normal office operations will resume on February 24, 2026 (the 8th day of the 1st lunar month). During the holiday period, routine business processing will be temporarily suspended. We will promptly respond to any inquiries or collaboration requests once we resume work. On this joyous occasion of the Spring Festival, our company extends festive greetings to all our valued customers. We deeply appreciate your long-term support and trust, and wish you a happy Spring Festival and smooth sailing in all your endeavors.


PDC Drill Bits Crossing Intersecting Formations: How to Avoid Damage Caused by “Instantaneous Overload”

In oil drilling operations, the transition zone where the drill bit moves from soft rock formations into hard rock formations (or vice versa) is often a high-risk area for drill bit damage. A recent study, using sophisticated digital simulations, has revealed the underlying mechanical mechanisms behind this phenomenon and proposed effective solutions.

Product Inquiry

Please fill in the question you’d like to consult about, and we’ll provide you with the appropriate product support based on your needs!